SkyAICampus
HomePracticeLearnCode LabFocus

Learn

HomePracticeConcept cardsCode LabSky Tutor

Review

Revise todayMistake notebookProgress

Focus

Campus ForestFocus roomsSquads

Questions or feedback?
support@skyaicampus.com

Keyboard shortcuts

  • Choose an answer1–4 or A–D
  • Check, then next questionEnter
  • Next hintH
  • Search cardsCtrl K

How this quiz adapts

3 fast right answers in a row: the next questions get harder. 2 wrong in a row: a little easier.

Hints and guesses still count, just a little less, so use them whenever you're stuck.

Sky Tutor

Stuck on an idea? Ask in your own words, or by voice.

Ask Sky Tutor
SkyAICampus
PrivacyTermssupport@skyaicampus.com© 2026 SkyAI Campus

New skill. A one-minute read first, then the question.

60-second card

Work per day

If a job takes n days, you do 1/n of it each day. Working with rates makes these sums easy.

  • 10 days for a job → 1/10 of the job per day.
  • Work done = rate × time.
  • More workers, fewer days: workers × days stays the same.

Example: 6 workers take 10 days: 60 worker-days. 15 workers need 60 ÷ 15 = 4 days.

Remember: Turn every time into a rate (job per day).

Common mistake: Averaging the days instead of adding the rates.